Erection of BFW Preheater, Water wall and Headers of Boiler, installation of Refractory of Secondary Reformer. March-2011
Erection of High Pressure Carbamate Condenser(HPCC) and High Pressure Stripper,Waste Heat Boiler under the supervision of BELLELI ENEGRGY CPE, Italy at Ashuganj Fertilizer and Chemical Company Ltd in May-June, 2013.
Erection, Installation and Commissioning of Nitrogen Generation Plant (Cryogenic Plant) under the supervision of CNP-Cryo, Netherland at Ashuganj Fertilizer and Chemical Company Ltd. in Jan-April,2014.
Replacement of Superheater Tube bundles I & II including associated headers, expansion joints and related casings of 196 MT/ Hr Boiler at Ashuganj Fertilizer & Chemical Company Limited, Brahmanberia, Bangladesh